The method of using the garbage incinerator includes the following steps:
Furnace wall descaling: after the fire is turned off and cooled down, the administrator needs to enter the furnace and scrape all the accumulated scale on the inner wall with a hoe and a shovel to ensure that the furnace is relatively clean.
Separation net to prevent leakage: for large self-combustion incinerators can be inserted vertically in the bottom of the furnace 3-4 10 cm diameter steel pipe to prevent the unburned garbage under the leakage.
Furnace ventilation: the use of iron bars in the furnace to play 3-4 “wind eyes”, so that the ash leakage, to ensure the smooth flow of air.
Slag removal at the bottom of the furnace: use hoe and shovel to shovel the ash and garbage residues deposited at the bottom of the furnace to the outside of the furnace, to ensure that the bottom of the furnace has enough ignition space and access.
Ignite the fire at the bottom of the furnace: Use flammable materials such as rotten furniture, rotten shoes, etc., pour diesel oil or waste engine oil to ignite the fire and burn the garbage at the bottom of the partition net.
Add fire to the furnace: After lighting the fire at the bottom of the furnace, shovel dry and flammable garbage into the furnace from the mouth of the furnace to make sure that there are enough combustible materials in the furnace, so that the temperature of the furnace rises rapidly.
Furnace bottom fire: add combustible and flammable materials to the bottom of the furnace at any time, and clean up the accumulated ash to ensure that the bottom of the furnace fire burns for more than 10 hours, so that the furnace temperature reaches more than 500 ℃, to realize the self-ignition of garbage in the furnace.
Precautions for the operation of the garbage incinerator:
Safe operation: must be strictly in accordance with the instructions for use, to ensure that the user can operate independently before delivery. Refuse to fill with high-risk and explosive materials.
Ignition sequence: open the top sealing cover of the reaction tank, fill in the material and ignite, close the sealing cover, turn on the fan to assist combustion, open the gas pipeline valve after 5 minutes, ignite the stove secondary combustion.
Shutdown sequence: close the gas pipeline valve, fan, open the bypass valve appropriate amount of ventilation.
Equipment maintenance: equipment power off in time to clean up the residue for the next time.
Through the above steps and precautions, you can ensure the normal use of waste incinerators and efficient operation.